09 Jan Paint or Flooring First? A Clear Step-by-Step Sequence
Renovating a room means juggling tasks in the right order. Get the sequence wrong, and you risk scuffed boards, touch-ups, and schedule delays. Below is a simple, reliable order that answers the big question—do you paint before flooring—and explains when exceptions make sense.
The Short Answer
In most projects, paint first, flooring second. Painting early protects your new floors from splatter, speeds up masking, and keeps cleanup easy. The main exceptions involve site-finished hardwood and major subfloor work, which may shift the steps (we’ll cover those cases below). For a deeper dive, see our guide on do you paint before flooring.
The Ideal Order (Standard Projects)
Follow this sequence for a typical repaint with carpet, luxury vinyl plank (LVP), laminate, or prefinished hardwood:
- Demo & Rough Work
- Remove old flooring, baseboards (if replacing), damaged drywall, and anything slated for disposal.
- Complete framing or electrical changes that affect walls or ceilings.
- Surface Repairs
- Patch drywall, sand smooth, and prime repairs.
- Caulk gaps at casing and trim that will remain.
- Prime (as needed)
- Prime new drywall or large patches now—no floors to protect, so prep is faster.
- A tinted primer helps when shifting from dark to light, or vice versa.
- Paint Ceilings
- Gravity wins—do ceilings first to avoid drips on fresh walls later.
- Paint Walls
- Apply two finish coats.
- Let paint cure per the label; good dry time here minimizes scuffs during flooring.
- Install Flooring
- Bring in and acclimate materials as required by the manufacturer.
- Install underlayment, then flooring.
- Install/Replace Baseboards & Shoe Molding
- Nail, fill, and caulk.
- Touch up nail holes and caulk lines.
- Final Touch-Ups & Cleanup
- Address light dings from installation.
- Reinstall switch plates and vents, then do a final wipe-down.
This order avoids heavy masking of brand-new floors and reduces the risk of adhesive or dust getting embedded in fresh paint.
Why Paint Before Flooring Works So Well
- Less Risk to New Floors: Paint spatter, roller spray, and ladders are easier to control when the floor is still bare or covered with expendable protection.
- Faster Prep: It’s quicker to mask along the subfloor or old carpet than pristine hardwood.
- Cleaner Lines at Base: When replacing baseboards, paint the walls past the previous baseline, then install new baseboards and caulk for a sharp finish.
- Smoother Schedule: Painters can finish ceilings/walls while flooring is still in transit or acclimating.
Important Exceptions (And How to Handle Them)
1) Site-Finished Hardwood (Sand & Finish On Site)
When floors are sanded and finished on site, the sequence changes:
- Do This:
- Demo and repairs
- Install raw hardwood
- First sanding & first coat of floor finish (sealer)
- Paint ceilings and walls (carefully protect the floor)
- Final floor coats after the wall paint is cured
- Baseboards/shoe molding, then touch-ups
- Why: The sanding process creates dust that can cling to fresh wall paint. Sealing the raw wood first locks the fibers down; then you paint, and the floors receive their final coats for a flawless finish.
2) Major Leveling or Subfloor Repair
If you’re using self-leveling compound or doing heavy subfloor work, complete this messy stage before painting so dust and slurry don’t contaminate the new paint. After repairs are cured, proceed with the standard “paint-then-floor” order.
3) Kitchens and Tight Remodels
When cabinetry or islands are involved, the floor is sometimes installed after base cabinets but before the toe-kick and shoe molding. Paint walls/ceilings first, install cabinets, set the floor, then finish trim and touch-ups.
What About Trim—Before or After Floors?
- Replacing Baseboards: Install after flooring. You’ll get tight joints, perfect reveals, and cleaner caulk lines. Paint or touch up the base once installed.
- Keeping Existing Base: If the floor height is changing, you may need shoe molding to cover gaps. Paint walls first, then floors, then the ceiling, then touch-ups.
Protecting Surfaces During Each Stage
- During painting, use rosin paper or drop cloths on existing floors you’re keeping. Tape only to stable surfaces—avoid leaving tape on delicate finishes for extended periods.
- During Flooring: Lay breathable protection (ram board or rosin) along high-traffic paths. Keep touch-up paint handy for small marks at the end.
Timing & Drying Tips That Save Rework
- Respect Dry Times: Even “dry to the touch” isn’t “ready for traffic.” Check the can for recoat and cure times, especially before installers bring tools and boxes over fresh paint.
- Ventilation Helps: Gentle airflow accelerates drying; avoid high-heat blasting, which can cause flashing or premature skinning.
- Box Your Paint: If you need more than one gallon, mix them in a larger bucket, so the color stays consistent from wall to wall.
A Simple Room Timeline (Standard Project)
Day 1: Demo, repairs, and primer on patches/new drywall
Day 2: Ceilings (two coats if needed)
Day 3: Walls (first coat)
Day 4: Walls (second coat) and dry time
Day 5–6: Flooring delivery/acclimation (varies by product)
Day 7: Flooring installation
Day 8: Baseboards/shoe molding; caulk and touch-ups
Day 9: Final walkthrough and cleanup
Your schedule may be condensed or expanded based on room size, product dry times, and crew size, but the sequence remains the same.
Common Mistakes to Avoid
- Flooring First on Standard Jobs: New floors invite paint splatter, ladder marks, and slow masking.
- Skipping Primer on New Drywall: You’ll end up with an uneven sheen later. Prime early.
- Forgetting Cure Time: Moving boxes or tools against walls too soon leads to scuffs you didn’t plan for.
- Painting Base Before Installation: If baseboards are new, install them after flooring for better joints, then paint or touch up in place.
- Ignoring Height Changes: Thicker floors can shift door clearances, baseboard reveals, plan transitions, and shoe molding.
Quick Decision Guide
- Standard LVP/laminate/prefinished hardwood? Paint first, then floors.
- Site-finished hardwood? Install/sand/seal walls; then paint walls, then apply final floor coats.
- Heavy subfloor leveling? Repair/level first, then paint, then floors.
- Replacing baseboards? Floors first, then base, then paint/touch-ups on base.
Cost & Quality Advantages of the Right Order
- Less Masking, Less Labor: Painters move faster without tip-toeing around new floors.
- Cleaner Lines: Baseboards installed after floors produce crisp, uniform caulk lines.
- Fewer Touch-Ups: Proper cure windows mean fewer return trips and a smoother finish overall.
- Better Protection: You’re not risking stains or dents on a brand-new surface.
Want a Deeper Dive?
We’ve outlined more pointers on our resource covering ” Do you paint before flooring—handy if you’re planning a multi-room schedule or mixing different flooring types.
FAQs
1) Should I remove the old carpet before painting?
Yes. Pulling the carpet first exposes the edges and tack strips, allowing painters to patch and paint to the final floor line without guesswork.
2) If I’m keeping my baseboards, when do I paint them?
After flooring is installed, add shoe molding (if needed), caulk, and then paint or touch up the base for a smooth, continuous look.
3) How long should the paint cure before floor installers arrive?
Follow the label instructions, but a common rule is that walls take at least 24–48 hours to harden enough to handle light contact. More time is safer in humid or cool conditions.
4) What if the flooring delivery requires acclimation?
Great—use that window to let the paint dry fully. Paint first, let it cure, then install flooring once acclimation is complete.
5) Can I paint baseboards before installing them?
Yes, you can pre-paint baseboards to speed up the process. After installation, fill nails, caulk, and do a final light coat for a perfect finish.

Mike Katounas is the owner of Home Works Painting, a painting business in Northern Virginia. He has over 15 years of experience in residential interior and exterior painting, drywall installation/repair, carpentry, wallpaper removal, power washing, commercial painting, color consultation, and staining/sealing. Their service areas include Chantilly, Fairfax, Herndon, Oakton, Reston. Mike takes pride in his work, and he always follows a strict code of conduct that includes the use of quality paint, a clean workspace, and an honest, respectful approach to his customers.